Saving on the Geotechnical Investigation – A False Economy

As a result of the additional investigation, serviceability end bearing pressures of 1 000 kPa, 2 000 kPa and 6 000 kPa were suggested for Class V, Class IV and Class III sandstone respectively.

Using the same quantities of work as for the initial investigation but including an allowance for rock coring in each bore, the cost of the field work, laboratory testing and reporting is estimated to be of the order of $15 000.

5. Revised Pile Design

As a result of the additional investigation, the Piling Contractor was able to redesign the piles with higher end bearing pressures and shaft adhesion. The redesign resulted in the same number of piles but with 121 piles of 600 mm diameter and 271 piles of 400 mm diameter. The revised pile design is given in Table 2.

 

6. Comparison of Pile Designs

The revised pile design generally reduced the pile diameters and, in many cases, decreased the pile depths. The most noticeable changes were Pile A which was reduced from 1050 mm diameter to 600 mm diameter and Pile J whose depth decreased from 9.4 m to 5.3 m. There were some significant changes. A summary of the quantities involved in both the initial and revised design is provided in Table 3.

On this particular project, the client saved approximately $5 000 on the geotechnical investigation by not coring the underlying bedrock. Due to the conservative recommendations contained in the initial geotechnical report, the cost of the piling works as initially designed was $620 000. However, if the client had spent the extra money, approximately $5 000, to core the rock and obtain more appropriate design parameters, the pile design would have cost $425 000 and occupied 19 days in the program.

Therefore an initial saving of $5 000 on the geotechnical investigation cost the client approximately $200 000 more in the long run. In other works, the additional piling costs were nearly 40 times the initial cost savings made during the investigation.

 

The redesign also lead to other savings such as the reduced time of site, reduced interest payment on loans, reduced site administration costs, etc. This can be significant on some site, especially where there is a tight construction program and/or high liquidated damage costs. The major saving on this particular site was the reduced time spent on the site as there was a tight construction program.

There were some other costs involved in that the piles had to be redesigned by engineers following an additional investigation and there was a delay on site while the redesign was being carried out. These costs were significantly less than the savings.

7. Comments

In this case, the initial geotechnical investigation was not able to properly assess the rock strength and defects within the bedrock because no coring of the rock was undertaken. Therefore it was not possible to assign rock classes to the bedrock. The cored bores, although more expensive to drill, provides a better assessment of the rock strength and allows for viewing the defects of the “in situ” rock. Once this information is obtained, it is possible to assign rock classes to the bedrock using the Pells et al method and provide more appropriate design parameters.

The initial design had a number of piles founded at depths greater than the depth of the initial investigation It would have been assumed that, based on the initial investigation, the sockets would be in medium to high strength rock although the design of the piles was based on design parameters appropriate for extremely low strength rock. The additional investigation established that the initial design would involve drilling sockets into high strength sandstone. This would have resulted in slower drilling rates, more time on site and a possible variation claim for different ground conditions to that reported in the initial investigation.

The original investigation was commissioned by the end client. In arriving at a decision, the client should be aware of the other factors such as long term cost implications, timing, availability, etc rather than just comparing prices. If in doubt, the client should ask his structural or civil engineers for advice and not be driven by price alone. In most things, you get what you pay for. A “limited” geotechnical investigation will generally provide “limited” advice or recommendations.

In most cases, a client will not realise the long term implications of his “initial” cost savings because he has nothing to compare it. He only has the recommendations of the one investigation and does not have the luxury of another, possibly dearer, investigation to compare other possible recommendations.

It raises the dilemma of how much do geotechnical engineers reduce the price (and consequently the scope of works) of geotechnical investigation to win a proposal knowing that it will probably cost the client more in the long run. In such cases, a geotechnical engineer should explain its limitations in the proposal.

If a client is totally price driven, he should be comparing “apples” with “apples” and provide a detailed schedule of rates rather than asking for a price for a geotechnical investigation.

8. Conclusion

It was only the astuteness of the piling contractor in this case which provided a cost saving of a significant amount of money. How the saving is distributed is another question and not discussed in this paper.

The above example shows the “savings” in investigation costs of approximately $5 000 nearly lead to costly foundation solutions, some $200 000 more expensive than necessary. Often, many clients are mislead in thinking that they are saving money, but as they do not carry out the comparison, they are unaware of the potential cost saving which can be made in the long run.

In addition to the actual cost of piling, there are also other factors such as site costs and construction program which can be adversely affected by “savings” made during the geotechnical investigation stage.

Each project is different and therefore the quantities will vary, but the principle is the same. However, it can be said that savings on many medium to large sized geotechnical investigations is often a false economy.

The above case reconfirms the conclusion of Phillips et al (1990), “Competent geotechnical input can provide significant cost savings during the course of a project, both at the feasibility and design stage, and during construction. The preparation of reliable and comprehensive site information will increase contractor confidence and reduce the risk of construction costs.”

References

Andrews, P., „The hidden cost of Geotechncial Investigations“, Australian Geomechnaics, Volume 41 No 4, December 2006 Pells, P. J. N., Douglas, D. J., Rodway, B., Thorne, C. and Burgess, B. K. (1978) “Design Loadings for Foundations on Shale and Sandstone in the Sydney Region.” Australian Geomechanics Journal, Volume G8, 31-39, 1978

Pells, P. J. N., Mostyn, G. And Walker, B. F. (1998) “Design Loadings for Foundations on Shale and Sandstone in the Sydney Region.” Australian Geomechanics, Number 33 Part 3 December 1998.

Phillips, A. B., Douglas, B. J., Fell, R., McMahon, M., Pells, P. J. N., Thorne, C., Turner., R., Walker, B., “The Geotechnical Consultant”, The Institution of Engineers, Australia, Civil College Technical Report April 6 1990.

Download the PDF here.

576-Young-Ellis